LINACRE RISE, HAMPTON – 3 LEVEL BASEMENT EXCAVATION

Project Overview
Starbuck Excavation delivered bulk and detailed excavation works for a 3-level basement at Linacre Rise, Hampton, supporting a large-scale residential development.

The project involved significant material removal within a constrained site, requiring careful planning and coordination to maintain the programme and support subsequent construction activities.

Scope of Works

  • Bulk excavation of approximately 31,500m³ for a 3-level basement 
  • Detailed excavation to final design levels 
  • Removal and off-site disposal of clean and mixed fill, including vegetation 
  • Bulk haulage and coordination of material export 
  • Operation of plant and equipment within a constrained site environment 
  • Coordination with site teams to maintain programme sequencing 

Key Challenges

  • Large-scale excavation within a multi-level basement footprint 
  • Management of varying material types (clean fill, mixed material, vegetation) 
  • Restricted access and working space 
  • Maintaining efficiency across bulk and detailed excavation phases 

Project Snapshot

Location: Hampton 

Scope: 3-level basement excavation 

Volume: ~31,500m³ excavated 

Material: Clean and mixed fill (non-contaminated) 

Outcome: Completed ahead of programme 

Capability Outcome


This project demonstrates Starbuck Excavation’s ability to deliver large-scale, multi-level basement excavations efficiently and within programme.

Through strong planning, experienced operators, and coordinated delivery, Starbuck completed the works ahead of schedule while maintaining quality and supporting downstream trades.