Project Overview
Starbuck Excavation delivered bulk and detailed excavation works for a 3-level basement at Linacre Rise, Hampton, supporting a large-scale residential development.
The project involved significant material removal within a constrained site, requiring careful planning and coordination to maintain the programme and support subsequent construction activities.
Scope of Works
- Bulk excavation of approximately 31,500m³ for a 3-level basement
- Detailed excavation to final design levels
- Removal and off-site disposal of clean and mixed fill, including vegetation
- Bulk haulage and coordination of material export
- Operation of plant and equipment within a constrained site environment
- Coordination with site teams to maintain programme sequencing
Key Challenges
- Large-scale excavation within a multi-level basement footprint
- Management of varying material types (clean fill, mixed material, vegetation)
- Restricted access and working space
- Maintaining efficiency across bulk and detailed excavation phases
Project Snapshot
Location: Hampton
Scope: 3-level basement excavation
Volume: ~31,500m³ excavated
Material: Clean and mixed fill (non-contaminated)
Outcome: Completed ahead of programme
Capability Outcome
This project demonstrates Starbuck Excavation’s ability to deliver large-scale, multi-level basement excavations efficiently and within programme.
Through strong planning, experienced operators, and coordinated delivery, Starbuck completed the works ahead of schedule while maintaining quality and supporting downstream trades.