MARCUS CONSTRUCTIONS – PORT MELBOURNE

Project Overview

Starbuck Plant Hire delivered large-scale contaminated material haulage and disposal services in Port Melbourne for Marcus Constructions, supporting site preparation within a constrained urban environment.

Scope of Works

  • Bulk haulage of contaminated material, including CAT B, CAT C, CAT D and asbestos-contaminated material
  • Coordination of disposal to approved facilities
  • Provision and management of compliant trucks and drivers, including subcontract fleets
  • End-to-end management of waste transport documentation and disposal records
  • Delivery in line with environmental and regulatory requirements

Project Snapshot

  • Location: Port Melbourne
  • Material Removed: Approx. 26,000 tonnes of contaminated soil
  • Programme: Bulk works completed within 2.5 months, with ongoing support thereafter
  • Scope: Haulage and disposal only
  • Project Value: Multi-million dollar contaminated material movement